# | Date Identified | Risk | Probability (1-9) | Impact (1-9) | Score (PxI) | Mitigation Plans | Closed/Open | Risk Owner |
---|
1 | 1/17/2023 | Final Report cannot be completed because we only have data from one partner for Year 1, HCN. |
|
|
| - Identify why we don't have data for Year 1 and establish next steps (Ray? Andrea?) AP thought we did have data that was shown in Harvest Meeting slides??
- Finish the Year 1 Final Report giving the data we do have so we can move on to Year 2.
|
|
|
2 | 1/18/2023 | HCN can't fulfill deliverables because they still do not have a contract. | 3 | 8 | 24 | - AP continue to write to CAD Business Operations to try to move the contract.
|
|
|