Round 1 – Notice of Funding Opportunity is released by CDC
Project Leads prepares work plans and budgets for the proposal based on the specific level of funding available
CAD leadership reviews, revises, and approves work plans and budgets
Finance (Director and CFO) provides a final review and approval of work plans and budgets
Grants Administration team uploads continuation work plans and/or CIO response to project plans to CSTLTS Recipient Dashboard and GrantSolutionsand when applicable to Grants.gov
Note: If it is a new CIO project, Federal forms are required to be submitted, as approved by CFO, in Grants.gov
Proposal Review Process
After submitted, CDC Technical Monitors reviews each project proposal
Notice of Awards – Once approved, CDC issues a Notice of Awards (NoA). The NoA details the amount funded for the project and provides guidance on any additional requirements for revisions or information.
Round 2 – Budget Revisions, Technical Reviews and New CIO Projects (i.e. supplemental proposals)
May be required for some proposals
CAD leadership and Project Leads revise proposals as needed and prepares new supplemental work plans and budgets as applicable
Once approved by CAD leadership, work plans and budgets are sent to Finance for approval
Grants Administration team uploads revised continuation work plans and/or CIO response to project plans to CSTLTS Recipient Dashboard and GrantSolutions and when applicable to Grants.gov
Proposal Review Process
After the revised project proposal /CIO project proposal is submitted, CDC Technical Monitors reviews each project proposal
Notice of Awards – Once approved, CDC issues a revised Notice of Awards (NoA).
Round 3 – New Funding/Supplemental Funding (if applicable)
CDC may have a third round of funding
Process for Round 3 is the same as Round 1 (see above)
...